Hot & Cold Weather Masonry Construction

Requirements

Table 1

Hot Weather Preparation and Construction Requirements
(ACI 530.1-98/ASCE 6-98/TMS 602-98)

Temperature Range
(Ambient)*
Preparation Requirements
(Prior to Commencing Masonry Work)
Construction Requirements
(While Masonry Work is in Progress)
Above 115°F
(46.1°C)

or

Above 105°F
(40.6°C)
with a wind velocity greater than 8 mph (12.9 km/h r)

Shade materials and mixing equipment from direct sunlight

Maintain sand piles in a damp loose condition

Provide necessary conditions and equipment to produce mortar and grout having a temperature below 120°F (48.9°C)

Use cool mixing water for mortar and grout

Maintain temperature of mortar and grout below 120°F (48.9°C)

Flush mixer, mortar and grout transport container and mortar boards with cool water before they come into contact with mortar ingredients or mortar

Maintain mortar consistency by retempering with cool water

Use mortar within 2 hours of initial mixing

Above 100°F
(37.8°C)

or

Above 90°F
(32.2°C)
with a wind velocity greater than 8 mph (12.9 km/h r)

Maintain sand piles in a damp, loose condition

Provide necessary conditions and equipment to produce mortar and grout having a temperature below 120°F (48.9°C)

Maintain temperature of mortar and grout below 120°F (48.9°C)

Flush mixer, mortar and grout transport container and mortar boards with cool water before they come into contact with mortar ingredients or mortar

Maintain mortar consistency by retempering with cool water

Use mortar within 2 hours of initial mixing

* The surrounding jobsite temperatures when preparation activities and construction are in progress.

Table 2

Hot Weather Preparation and Construction Requirements
(ACI 530.1-98/ASCE 6-98/TMS 602-98)

Temperature Range
(Mean Daily)*
Hot Weather Protection Requirements
(Newly Completed Masonry Construction)
Above 100°F
(37.8°C)

or

Above 90°F
(32.2°C)
with a wind velocity greater than 8 mph (12.9 km/h r)

Fog spray all newly constructed masonry until damp, at least three times a day, until the masonry is three days old
* The temperature calculated to be the average of the extremes forecast by the local weather bureau over the next 24 hours.

Return to Hot & Cold Weather Masonry Construction

Mason Contractors
February 2025

NETWORKING It’s not just who you know, it’s who they know. Build deep industry relationships with the most connected professionals across the nation. CREDIBILITY Demonstrate your company’s commitment to excellence in craftsmanship, ability to stay up

Masonry Industry Links
April 2024

Masonry Industry Links

SINGLE WYTHE: REINFORCED BRICK
March 2024

This efficient and economical masonry system allows a single layer of brick to perform as both the structure and the exposed surface of the wall.

Concrete Block Veneer / Steel Stud
March 2024

This versatile wall system features a durable, low-maintenance masonry façade with a steel structure.