We Don’t Have a Manpower Problem, We Have a Production Problem

Words: Bronzella Cleveland
By Justin Breihaupt Jr., Owner of Non-Stop Scaffolding, Inc. One of the most popular events at the World of Concrete is the Fastest Trowel on the Block. You have several teams consisting of one bricklayer and one tender, each building a 30-foot- long 8-inch block wall, as high as they can go, in 20 minutes. Each bricklayer usually lays about 120 blocks. Then they get an extra 4 minutes to strike the joints. At the end of the build, the wall is judged on quantity, level, plumb, bond, straightness, etc., and the winner gets a big prize. That’s 120 blocks, laid correctly, in 24 minutes. Can an average bricklayer do that in 4 hours? Easily. Can an average bricklayer do that twice in 8 hours, making 240 for the day? Absolutely! Hold that thought. Where Did The Bricklayers Go? For the past couple of years there has been plenty of work, but not enough bricklayers. There is definitely a shortage. When the Great Recession hit, maybe they turned to other jobs, but the sheer number of available bricklayers is way down. The longterm solution, of course, is to attract young people to the trade and train them, but what do we do right now when we simply don’t have the manpower to do the work under contract? If we have to make do with the number of bricklayers we have now, we simply have to find a way to get more production from them. Increasing Production is the Way Forward This was one of the topics at the roundtable discussion at the MCAA 2018 Midyear Meeting in Austin, Texas. Let me stop here and say, if you aren’t going to the roundtable networking sessions at the midyear meeting and the annual MCAA meeting at the World of Concrete, you are seriously missing out. The knowledge you gain from your fellow mason contractors during these three-hour brainstorming sessions (on everything from silica to insurance) is completely worth the plane trip and hotel bill. But I digress. Part of the discussion was about production incentives and how employees of the company were compensated based on bringing a job in faster and under budget. For instance, Kent Bounds of Brazos Masonry discussed how their job superintendents were bonused 10% of the additional profit earned over the estimated profit in a given job. If the superintendent used his skill to manage the job day to day getting more production, and it made $100,000 more than estimated, he got a check for $10,000. Having been in the masonry business with my dad for many years, using an extremely successful bonus system the whole time, I listened curiously for exactly how their incentive systems worked. Some talked about issuing bonuses at year end depending on the company’s overall profitability that year. Some talked about doing it quarterly. But, they all agreed it is a win-win proposition all the way around. When you compensate your men based on their production, production and profit always go up.
Here is What is Really Possible What I’m about to say is going to blow your mind and possibly have you questioning my credibility, but it’s true. Please follow along and don’t dismiss this article until you’ve read it through and looked at the tables. I’m in a position to talk to hundreds of masonry contractors a year, and I always ask them if they use an incentive system. Only about 5% say they do. Those that do are getting incredible production and very high profits. There are mason contractors out there who routinely get 1,600 modular brick and 400 to 500 8-inch block per man per day. When I ask the 95% if they have ever played with the numbers to see if a bonus system would pay off, they say something like, “My guys are getting paid enough, I can’t afford anymore.” or my all-time favorite myth “A man is only going to give you so many brick in a day.” How It Works The most effective incentive systems rely on one simple truth: We only get paid based on materials in place. The faster the bricklayers lay, the bigger the draw. Theoretically, if the bricklayers lay twice as fast as we estimate, you cut both the job duration and the labor money spent almost in half. Now, if this really happened, you might have to hire a few extra laborers to tend these super-bricklayers, maybe another mixer man, and maybe another forklift operator to deliver the materials, but still, you’re talking about saving a whopping amount of labor. Let’s look at an example of a simple brick job. I polled a few mason contractors in Texas after the midyear meeting and asked them how they estimate their brick jobs. Bricklayers make $25 an hour. They figure they’ll get 550 brick a man a day. They figure brickwork at $13.20 a square foot labor, and $8.80 a square foot materials. For a job with 276,000 brick, that’s about $900,000 L&M. Add 10%, $90,000, for OH and profit and you’re at a $990,000 bid price. Now check out the table below. Line 1 shows that if the job goes as planned and the bricklayers lay 550 a man a day, you’ll spend the actual labor money estimated, and make the actual $90,000 profit. Now, just to check the math used in the table look at line 12. If they lay twice as fast as estimated (1100 a day instead of 550), the job will be over in half the time and you’ll spend half the estimated labor (sure, as above, you won’t cut ALL the labor in half, but pretty very close to it). The other half of the labor, something less than $270,000, becomes profit (in addition to the $90,000 profit estimated). Look at line 3. Adding only 100 brick a day shortens your job duration enough to darn near double your profit. When you start taking small chunks out of the big number - labor, and add it to the relatively small number - profit, you start to see how small reductions in labor turn into huge additions to profit.
BRICK JOB WITH 276,000 BRICK
A
B
C
D
E
F
Materials:
$360,000
Labor:
$540,000
OH & Profit:
$90,000
Total Bid:
$990,000
Projected Brick Per Man Per Day
Actually Laid Per Man Per Day
Percent Production Increase
Actual Labor Cost
Extra Profit Generated
Total Profit
1
550
550
0%
$540,000
$0
$90,000
2
550
600
9%
$495,000
$45,000
$135,000
3
550
650
18%
$456,923
$83,077
$173,077
4
550
700
27%
$424,286
$115,714
$205,714
5
550
750
36%
$396,000
$144,000
$234,000
6
550
800
45%
$371,250
$168,750
$258,750
7
550
850
55%
$349,412
$190,588
$280,588
8
550
900
64%
$330,000
$210,000
$300,000
9
550
950
73%
$312,632
$227,368
$317,368
10
550
1000
82%
$297,000
$243,000
$333,000
11
550
1050
91%
$282,857
$257,143
$347,143
12
550
1100
100%
$270,000
$270,000
$360,000
Chart number 1 showing the effect on job profit of extra production over estimated production.
How To Do It It is my personal opinion, based on years of experience and talking to other mason contractors, the best incentive systems compensate the bricklayers directly. After all, they are the men laying the units that put the extra money in the bank. I’m not saying to bonus only the bricklayers, just that the most successful systems always include the bricklayers. Now, the next logical question is, “How do we get the bricklayers to work faster?” Believe me, they can, remember the Fastest Trowel? The answer is to pay them for extra material over the “breakeven” amount in your bid. In our example job, your labor cost is $1.95 per brick ($540k labor / 276k brick). Give the bricklayers an extra $.50 per brick (or more) above 550 and they will produce like crazy, with no difference in quality. Remember, any time you’re paying bonus, your estimated profit is guaranteed. Take a look at the same job in the chart below. This time we give the bricklayers extra money in order to get the higher profit. The bricklayer on line 4 is laying an extra 150 brick a day which makes him an extra $75 a day, in addition to his $200 wages. It’s easy for him. He loves this. Pay their bonus on a separate check, preferably a different color. I know it’s easier to add it to their regular check, but don’t. This keeps it fresh in their minds that this is additional money they earned by working faster. It will also motivate others who notice the extra check to hone their skills and become a bonus bricklayer. The Bonus money goes into a weekly pool and it’s divided equally at the end of the payroll week. This is mandatory. Why? Bricklayers live paycheck to paycheck. Telling them to work faster and they will get a bonus at the end of the job, or the end of the year, does not work. You have to pay the bonus weekly. If they have a week that falls below breakeven, forgive it and move on. Wipe the slate clean every week. If they have a bunch of slow work in a job (like planters in a mall or bathrooms) you’ll see them put that all in one payroll week.
BRICK JOB WITH 276,000 BRICK
A
B
C
D
E
F
G
Materials:
$360,000
Brick in Job:
276,000
Labor:
$540,000
Bonus/brick over 550:
$0.50
OH & Profit:
$90,000
Total Bid:
$990,000
Projected Brick Per Man Per Day
Actually Laid
Percent Production Increase
Actual Labor Cost
Extra Profit Generated
Bonus Paid To Bricklayers
Total Job Profit
1
550
550
0%
$540,000
$0
$0
$90,000
2
550
600
9%
$495,000
$45,000
$11,500
$123,500
3
550
650
18%
$456,923
$83,077
$21,231
$151,846
4
550
700
27%
$424,286
$115,714
$29,571
$176,143
5
550
750
36%
$396,000
$144,000
$36,800
$197,200
6
550
800
45%
$371,250
$168,750
$43,125
$215,625
7
550
850
55%
$349,412
$190,588
$48,706
$231,882
8
550
900
64%
$330,000
$210,000
$53,667
$246,333
9
550
950
73%
$312,632
$227,368
$58,105
$259,263
10
550
1000
82%
$297,000
$243,000
$62,100
$270,900
11
550
1050
91%
$282,857
$257,143
$65,714
$281,429
12
550
1100
100%
$270,000
$270,000
$69,000
$291,000
Chart number 2 showing the effect on total job profit when an incentive system is in place.  
Give Them The Equipment They Need You can’t get much beyond line 4 on conventional frames. It’s too much bending and stooping, running scaffold-high and moving, and stop/start to hop planks. Plus, constantly tearing down and re-building conventional frames on a bonus job will eat you alive in labor. Crank-up scaffolding 45 feet high moves from wall to wall with a forklift at the rate of 90 feet an hour. That’s about 1/6 the moving cost of frames. To get past line 4 you need crank-up scaffolding or mast-climbers. Just imagine how many brick a man can lay in a day if he is laying a theoretical straight wall, waist-high, 2000 feet long, and never having to stop. He keeps his momentum. When they are on elevating scaffolding, there is a lot less work for the laborers, too - just crank for three minutes and tend the bricklayers for 20 minutes. Your New Job Site Culture Will Emerge I remember back when my dad told his men his new Bonus System, even bricklayers who had been with him continuously for years thought he was crazy. It took them a solid month of getting bonus checks to realize it was for real. They couldn’t understand how he could pay them this additional money, so he sat down with any of them who wanted to see the numbers and showed them how if they made $100 in bonus, he made $100 in additional profit (he gave them half of labor saved. So, if a 10-man crew made $100 each in bonus, he made $1000. He was literally splitting his extra profit with them. As a result, they developed a new trust in him. Morale and loyalty will go up to a new high. They all thought they were underpaid - now they’re working for a company who truly pays them what they’re worth. Production goes way up with no loss of quality. They were capable of it all along. This might make you very mad, but shake it off, chalk it up to human nature, and focus on your new-found profits. Your men will start to solve their own problems - problems that used to kill a lot of your time. They’ll take their breaks on the scaffold, or not at all. Your jobs will run as if you were there all day. Some superstar producers will emerge who match their paychecks with bonus checks and insist on working together. Accommodate them. It will snowball. Any new bricklayer who doesn’t produce usually won't last a day on a bonus job. The men on the wall will tell the foreman to get rid of him at the first break (because that man is costing them money). You will hear about it before lunch when the foreman calls in for the new man's check. If you need more bricklayers, your men will get them for you. They will bring you bricklayers who are faster than they are (so they don’t drag the countdown). If you have to lay some men off, they will always come back when you get more work because you pay more than anyone else. They will leave where they’re working and come back to you. Tips And Tricks They will develop tricks to work more efficiently. For instance, our bricklayers only cut their mortar off once. They got enough to throw a head joint and kept moving. They got the rest with their jointer as they struck the joints.
Some bricklayers gave the laborers a little money each day to strike up and hand them brick. When we went non-union, we hired guys to do that, especially summer help. Many of them came back to learn to lay brick with us because we paid so well. On a school job, for instance, you’ll see one crew set up with a different breakeven for the inside corridor block walls, and a different crew for the exterior brick. Maybe This is How We Grow The Workforce I truly believe that companies who adopt a performance-based pay system can use it to attract new apprentices to the trade. If bricklayers become the highest paid trade, we can assure a steady supply of manpower for the future. Sidebar: 
Justin Breithaupt, Sr. (1930 - 2017) was an innovative mason contractor in Shreveport, LA from 1954 to 1983. His passion for efficiency and higher production lead him to create corner pole systems, different material handling systems, and his own scaffolding system now marketed as Non-Stop Scaffolding. When Justin created his bonus system in 1969, it magnified the need for a new scaffolding system. He finally perfected it in 1976 and offered Non-Stop Scaffolding to his fellow mason contractors. It quickly began to out-pace Justin Breithaupt Masonry, Inc. When a horrible building recession hit the South in the early ‘80s, Justin transitioned over to scaffolding full- time. Though he loved his masonry business and threatened to start it up again, he never did. Justin’s contributions to the masonry industry earned him a spot in the Masonry Hall of Fame in 2017.
2024 Architectural Awards: Excellence In Masonry Winners

The Masonry Advisory Council held the 2024 Excellence in Masonry Awards on Saturday, October 26th at 167 Green St., Chicago, Illinois. Honoring 80 projects from over the Chicagoland and Northwest Indiana Area. The Awards program celebrates outstanding ar

NSI and ISFA Announce Silica Exposure Literature Review

NSI and ISFA are proud to present a literature review that summarizes the growing library of studies related to respirable crystalline silica (RCS) exposure. Completed by Yale Occupational and Environmental Medicine, the study covers 34 publications and d

La Maison Franchère: How Masonry Turns Functional Buildings Into Timeless Beauty

La Maison Franchère, or the Franchers’ House, stands as a notable relic of stone architecture in Saint-Mathies, a small Quebec town on the edge of the Richelieu River. Unlike the neighboring homes, this towering, two-and-a-half-story mansion immediately c