12 Story High Rise
TOPS OUT IN 92 WORKING DAYS
Edgewater Tower, West Haven, Connecticut

Mason Contractor: John Civitillo, Inc.
General Contractor: Dwight Building Company
Architects: Peter Kosinski Associates
Structural Engineers: Gensert Peller Associates

The construction industry in Connecticut is marveling at the speed of erection and low cost of a 12-story condominium apartment building which topped out in 92 working days at 1 Campbell Avenue in West Haven, Connecticut. The owner is Properties Corporation of America.

Designed by Architect Peter Kosinski Associates, of New Haven, Edgewater Tower sped skyward with one 13,270 sq. ft. floor of interior and exterior walls, including stairways, balconies, and floor system, completed every 6 1/4 days. Gross-foot cost for these superstructure components was an unbelievably low $6.60, according to Eugene Burian, speaking for Mason Contractor John M. Civitillo, Inc. Total cost for the completed building, without land cost, is budgeted at $3.5 million, according to Properties Corporation of America.

"This feat was not accomplished with a hum-drum design providing simple construction either," according to the International Masonry Institute (IMI), "for Architect Peter Kosinski departed from the square and rectangle too often associated with loadbearing masonry. Instead, he took advantage of the flexibility of masonry and designed a structure that will be noted for its unique architecture for decades to come," says IMI.

The 12-story 172,487 sq. ft. Edgewater Tower has 105 one and two bedroom apartments. It's exterior walls are of split-rib customized concrete masonry. One of the nation's top engineering firms, Gensert Peller Associates of Cleveland, served as Structural Engineers. The Mechanical Engineers were Lawrence G. Spielvogel, Inc., of Hartford.


Business Building: Top Field Systems To Achieve Results!
May 2025

To be successful in the construction business, you must achieve the field results you want to achieve. Therefore, what systems and standards do you have, maintain, train, and enforce which will almost certainly guarantee you will finish your jobs on time,

Marvelous Masonry: The Technical Administration Building, Frankfurt, Germany
May 2025

The Technical Administration Building in Frankfurt, Germany, is a testament to masonry construction's craftsmanship and durability. This iconic structure reflects the architectural trends of its era and serves as a case study in masonry preservation and r

Contractor Tip of the Month: Making Yourself Available for What Matters Most
May 2025

Your responsiveness is a key factor in achieving success in your career. Opportunities don’t wait, and neither do customers, employees, or critical decisions. Prioritizing accessibility, especially during pivotal moments, can be the difference between sec

Fechino Files: Differences
May 2025

I recently traveled to a city where I met with several contractors. After we talked a bit, several of the folks showed me around their places, and I saw two different ways of thinking based on the employees' personalities. I am sure you are wondering wher