CASE STUDY

HARDSCAPING
Segmental Retaining Wall Units and
Pavers Create Usable Space

For many years, hardscape products - segmental retaining wall and pavers - have allowed municipalities, commercial builders, developers and home owners ways to create usable space. With the many different shapes and types available, you can turn an ordinary backyard into an elegant and relaxing space to entertain. A commercial property can allow for structures, parking and traffic control, while municipalities can address stormwater management. The following case studies show how hardscape products can turn ordinary and, many times, challenging spaces into an eco-friendly environment.

HIGH POINTE COMMONS, HARRISBURG, PA.

This shopping/lodging complex is constructed on a hillside, which included challenges for retaining the earth to create the parking area, numerous walls surrounding the streets constructed to control traffic and water issues, and a parking lot surcharge on the main large wall. Six separate segmental retaining walls of various heights and lengths were engineered and constructed. The largest wall, supporting the parking lot for the Sheraton Hotel, was designed to address two major factors: handling the storm water drainage for the parking area above and the weight of vehicles being parked in the lot. It also was constructed along the newly designed street that would see a significant amount of traffic and to provide access by stairs to the shops for the residents of the hotel.

This project required the installation of more than 2,000 feet of fencing and handrails. The wall installer worked with the designer and railing installer in advance of the wall construction to coordinate the depth and location of each post footing that needed to be worked into the wall. The entire project team-excavation, utility installation, material storage, railing installation, and final grading met in advance to coordinate the scheduling of the various stages and construction of the site.

SPRING CREEK HOLLOWS DEVELOPMENT BRIDGE

A structure was needed to span a creek while supporting a main roadway in the residential development of Spring Creek Hollows, located in south central Pennsylvania. The walls were built in a 100-year flood plain, so the backfill material was all #57 stone wrapped in filter fabric up to one foot above the flood elevation. With a 39-foot, two-inch span, the structure serves as a wildlife underpass, reducing the number of animals crossing the road that could potentially cause a hazard to the animal and to traffic. It was necessary to build in late-fall and winter, under some very cold weather conditions, which played a part in the considerations as well.

The decision was made to use a super span metal plate, because of its capacity to support a large amount of fill in a cost-effective manner. The segmental retaining wall units were used as wing walls, which provided the required aesthetics and addressed the retained earth issues. The total wall area installed was 9,428 square feet, including caps for both walls (both ends of structure). A concrete swale was poured directly behind the cap units to divert the surface water runoff.


What gives with head protection? Why workers want to keep their hard hats and ditch safety helmets.
April 2025

Last August, I took my pickup to the dealership for a nagging check engine light. While it was being looked over, I chatted with the salesman I normally deal with, and he told me about the latest and greatest 2025 models. He told me how the twin turbo inl

Government Affairs: Bringing North Carolina to Washington, D.C. and Hopefully Young People to Your Jobsites
April 2025

For you long time members of the Mason Contractors Association of America you likely remember our Annual Washington, D.C. Fly-In where MCAA members from around the country would come to Washington, D.C. meeting with Members of Congress from their home sta

Chairman's Message: While We Are Still Here
April 2025

I truly value my days working on construction sites during the summers of my high school and college days. Some moments in our youth are so clearly meaningful that we file them away in our subconscious to be recalled when life events require inspiration.

Contractor Tip of the Month: The Tough Calls That Define a Leader
April 2025

In construction, every project balances a delicate trio: coordination, precision, and timing. However, beyond blueprints and schedules, leadership demands something far greater—the ability to lead and make difficult decisions that shape the future of a co